Randwick update
7 June 2019Light rail reached an important milestone in Randwick early in May with the start of day testing. This means day and night systems and tram testing is underway in Randwick.
Construction crews in the area are now focussed on finishing works including landscaping.
End-state traffic conditions are now in place in Randwick so take extra care when travelling in the area as traffic conditions have changed and new traffic lights are now operating.
Ausgrid high voltage work is progressing along High Street, Clara Street and Arthur Street.
Construction compounds are being dismantled in High Cross Park to facilitate the completion of landscaping.