The construction team is busy with finishing works in Kensington and Kingsford. These include pram ramp finishing works, sealing pavements, final landscaping, installing remaining tactile pavers in Kingsford, and cleaning footpaths and stops.

The team is also reinstating Tay Reserve. This work includes installing a new bus stop, and vegetation works.

Footpath reinstatement and paving works have been completed as well as vegetation planting and landscaping. Bus shelters, tactile pavers and signage works have also been completed.

Tram testing and commissioning, and driver familiarisation of the route is progressing so more trams will be travelling along Anzac Parade to Juniors Kingsford terminus in the coming weeks.