Teams will be completing drainage in the coming weeks in the precinct as they turn their attention to installing overhead wires. Upcoming works also includes landscaping, footpath and road restoration.

Delineation is being installed between Alison Road and Abbotford Street at the southern end to facilitate end-state traffic in zone 28.

In zone 29 works are moving ahead at the Kensington stop with delineation kerb installed nearby. Works on traffic signals at pedestrian crossings and landscaping are also underway. The footpath between Duke Street and Balfour Lane is complete.

Footpath works are also progressing along Anzac Parade on the western side between Doncaster Avenue and High Street.

In zone 30, paving has been completed around the northwest side of Strachan Street and will progress around the Kingsford stop and Nine Ways. Traffic islands have been completed and work on end state traffic signals is underway.

Paving is also continuing in zone 31. Work will progress to reinstate footpaths and roads ahead of a traffic switch at Sturt Street in the coming weeks.