VIDEO: Making tracks in Moore Park

3 August 2018

Take a look at the latest time lapse video of double track being laid in the Moore Park tunnel.

Crews made the most of weekend lane closures along South Dowling Street to progress with track installation at this complex road crossing between zones 19 and 20, which is nearing completion.

Teams are focussed on finishing works at the Anzac Parade and Lang Road intersection in zone 21, with the final configuration ready in the coming weeks.

Works are also progressing on the pedestrian bridge in zone 22.1 with piling works scheduled for completion ahead of demobilising the piling rig and crane.

Zone 22.2 sees progressive works at the Anzac Parade, Alison Road and Dacey Avenue intersection with night time lane closures over the next few months.

Anzac Parade southbound lanes will be temporarily moved west to complete track slab and pavement works for the permanent southbound lane.

For the latest construction notifications visit our library.