Video: CBD intersection milestone

11 May 2018

April saw the start of construction work at the intersection of Park, George and Druitt Streets and means that all intersection works in the CBD are now underway. The work at this intersection included investigations and kerb demolition.

Preparation work was undertaken during April for the smart poles which will be installed to provide street lighting on George Street between Goulburn and Bathurst Streets.

Stormwater works continued at the Hunter Street and Margaret Street intersection, while in zone 4, George Street between Margaret Street and King Street, 60 metres of double track were installed.

Zone 10, George Street between Goulburn Street and Hay Street, surpassed 60 per cent of track slab in place.

Over the Easter break, construction crews worked on seven intersections along the alignment: Market and George Streets; Bathurst and George Streets; Devonshire and Elizabeth Streets; Devonshire and Kippax Streets; Bourke and Devonshire Streets; Alison Road / Davey Avenue and Anzac Parade; and High and Botany Streets.

Track was also completed across the complex intersection at Market Street in the CBD.