Randwick work moving ahead

4 April 2018

Crews continued to install track in Zone 26, High Street between Wansey Road and Avoca Street during March. This included installing track across the Botany Street and High Street intersection over the Easter weekend.

Crews are continuing with stakeholder communications and work on the stormwater drain in the zone as they work towards two partial shutdowns at the intersection of Avoca Street and High Street in April.

Stormwater works is also taking place on Cuthill Street in Zone 27, High Cross Park. An unexpected utility find has impacted the work, with completion due in April.

Two sections of the Randwick Stabling Yard are now energised. Altrac are continuing to test electrical systems and light rail vehicles as part of this phase of the CBD and South East Light Rail project.

Next month Altrac are planning to undertake utilities and systems work at the Doncaster Avenue entrance.

Crews are continuing work on the track power supply in the zone and are starting stakeholder communications as they work towards two partial shutdowns at the intersection of Avoca Street and High Street and intersection of Belmore Road, Avoca Street and High Street in April.

In Zone 25, Wansey Road between Alison Road and High Street, around 70 metres of track is left to be laid and this is expected to be completed in early May.