Moore Park progress

26 June 2018

Track was successfully installed across the Alison Road / Dacey Avenue / Anzac Parade intersection in zone 22 over the June long weekend.  Additionally, track is being installed in the Moore Park tunnel.

Preparations have started ahead of piling works for the pedestrian bridge over Anzac Parade. Bore piles for the bridge have started with concrete formwork for columns and headstocks (horizontal structures that transfer loads from the deck to the columns) taking place in the coming weeks.

On Alison Road, between Darley Road and Doncaster Avenue, traffic lanes have been temporarily reduced to enable watermain works.