Moore Park moving ahead

28 October 2018

Tramway Oval reinstatement is progressing in zone 20, with the temporary pedestrian diversion now closed. Pedestrians instead are directed to the end-state footpath along Anzac Parade, between Tibby Cotter Bridge and Sydney Boys High School.

Upcoming work in the zone includes progressing systems cabling work from zone 19 into Moore Park to power the light rail vehicles.

Work is also progressing on the Moore Park light rail stop with the platforms and structural steel frame completed.

Signal work is progressing in zone 23 alongside end-state landscaping works on Alison Road between Doncaster Avenue and Darley Road. The team also facilitated a traffic switch to the end-state lane set up. Upcoming work in the zone includes opening the new access road into the Australian Turf Club. Work on Royal Randwick light rail stop is progressing with skylights installed and electrical wiring completed.