Moore Park construction progress

4 April 2018

In Zones 20 and 21, between the Eastern Distributor and Lang Road, excavation work for the operational control centre at the Moore Park stop was completed. April works will include the installation of steel frames as the stop continues to take shape.

The Alison Road, Anzac Parade and Dacey Avenue intersection in Zone 22 saw the removal of old tram slab on the southern side complete.

The permanent bicycle/footpath change along the embankment started at Easter in Zone 23, Alison Road, between Anzac Parade and Darley Road.