Altrac and their contractors have been carrying out works at the Lilyfield depot, completing the retaining wall in the middle of the site and starting work on another retaining wall in the site.

March saw progress on the maintenance building piling and earthworks in the northern zone.

The substation is nearing completion with final details to be finished in the coming months.  