CBD construction update

31 May 2018

Activity in the CBD zones this past month included concrete pours and track laying.

In zone 4, George Street between Hunter Street and King Street, the team commissioned the Multiple Service Board on Barrack Street at the end of May.

This Multiple Service Board will power the traffic light signals as well as the new smart pole street lights in the area.

A second Multiple Service Board is also underway in zone 9, George Street between Liverpool Street and Goulburn Street to power traffic light signals and smart poles.